AS 3610 is the Australian Standard series for formwork for concrete. AS 3610.1:2018 sets out the documentation formwork design relies on and how off-form concrete surfaces are specified and evaluated, including five surface finish classes. AS 3610.2 (Int):2023 sets minimum requirements for designing, erecting and removing formwork.
This guide covers what a project team needs settled before the first panel goes up: which document governs what, what the finish class does to the formwork, who signs, and what a design package contains. It builds on formwork safety and structural compliance in Australia.
Key takeaways
- AS 3610 is a series. AS 3610.1:2018 covers documentation and surface finish, AS 3610.2 (Int):2023 covers design and construction, and AS 3610-1995 remains listed as current in part.
- The finish class drives the formwork. Class 1 is the most demanding and Class 5 the least. Classes 1 to 3 apply where appearance matters.
- There is no fixed price per class. Form face, detailing, workmanship and inspection decide the cost.
- Name every role. Preparing, checking, certifying, approving and verifying a design are separate tasks.
- A design package is a coordinated set. Drawings, calculations, schedules and sequence documents must agree with each other and the structural drawings.
- Sign-off depends on the project. WHS law, the NSW Code of Practice, the specification and the contract together decide who certifies what.
What does AS 3610 cover?
AS 3610 covers the information needed to design formwork, the requirements for designing, erecting and stripping it, and how the formed concrete surface is specified and assessed. The series is split across parts:
- AS 3610.1:2018, Part 1: Specifications. Architectural, structural and construction information for formwork design, and the quality, tolerance, colour and evaluation of off-form surfaces.
- AS 3610.2 (Int):2023, Part 2: Design and construction. An interim Standard covering design, erection and removal for cast in situ concrete.
- AS 3610-1995. The original combined Standard. Standards Australia still lists it as current, with AS 3610.1:2018 superseding its Sections 2 and 3 and Clauses 4.7 and 6.
Specify the finish before formwork design starts. The class sets the form face, panel layout and tie positions, and those are expensive to change once built.
What is the difference between AS 3610 and AS 3610.1?
AS 3610.1 is Part 1 of the AS 3610 series and deals with what must be documented and specified, including surface finish. Design and construction now sit mainly in AS 3610.2 (Int):2023. Standards Australia notes the parts were intended to coexist while the series review continues.
The specification should name the parts and editions that apply, and the formwork designer should state which ones the design relies on. Requirements such as sample panels or repair limits may come from the project specification. They aren’t automatically AS 3610 requirements, so confirm editions and amendments at tender and again before design.
What are the concrete surface finish classes under AS 3610?
A surface finish class defines the quality an off-form surface must achieve. AS 3610.1 sets five classes, from Class 1 (highest) to Class 5 (lowest). According to the National Precast Concrete Association Australia, Classes 1 to 3 apply where visual quality matters and Classes 4 and 5 where it doesn’t. The classes cover off-form surfaces only, not polished, honed, grit-blasted or acid-etched finishes. Show the class for each element on the drawings and in the specification.
Table 1. AS 3610 concrete surface finish classes compared
| Class | Finish expectation | Typical application (industry guidance) | Formwork and form face | Workmanship and quality control | Relative cost |
| Class 1 | Highest standard, most rigorous inspection | Special features of monumental buildings, small elements, single pours; not whole elevations | Purpose-selected face; formply not recommended | Tight control of placement and curing; sample panels advisable | Highest cost and risk; often over-specified |
| Class 2 | High quality, viewed in detail | Façades seen up close | High-grade face; joints and ties set out with the architect | Substantial design input; close pre-pour inspection | High form-face use, detailing and inspection |
| Class 3 | Good quality viewed as a whole | Visible structures of lesser architectural importance | Good face, sealed joints; fewer defects allowed than Class 4 | Consistent good practice | Often the cost-effective visible finish |
| Class 4 | Visual quality not significant | Surfaces concealed from general view | Face chosen mainly for structural and dimensional performance | Dimensional and structural checks | Lower finish cost |
| Class 5 | Visual quality not significant | Surfaces never seen | Lowest finish requirement | Dimensional and structural checks | Lowest finish cost |
Summary of industry guidance from National Precast, the Big River Group off-form white paper and the EWPAA formply technical note. It does not reproduce the Standard. Confirm acceptance criteria against AS 3610.1:2018 and the project specification.
How does the finish class affect formwork design and cost?
The higher the class, the more the formwork is designed around appearance as well as strength. Form face material and condition, panel layout, joint and tie positions, tolerances, pour rate, vibration, curing, inspection and repair limits all tighten. The choice between formply, steel and aluminium form faces often turns on this, because a Class 2 formply face may give only one reliable Class 2 pour.
So what does each class cost? There is no universal price, and the scale isn’t linear. Moving from Class 3 to Class 2 can change the form face, detailing, labour and inspection all at once, while moving from Class 5 to Class 4 may change little. Price each project from its specification, geometry, form-face strategy, access and quality assurance.
Who is responsible for formwork design in Australia?
The party engaged to design the formwork is responsible for the design, within duties set by WHS law and the contract. Under section 22 of the WHS Act, a business that designs a structure for use at a workplace has its own duties. The NSW Formwork Code of Practice says the designer must do enough calculation, analysis or testing to show the formwork can safely carry its loads.
- Principal contractor: manages the work, plans the sequence and coordinates duty holders.
- Formwork contractor: builds and strips the formwork to the design.
- Formwork or temporary works designer: prepares the design and documents its assumptions and limits.
- Structural engineer: designs the permanent structure, which shapes the formwork but doesn’t make them its designer.
A builder’s approval doesn’t remove the designer’s duties, and an internal review isn’t independent certification. Competent site leadership matters too, which is why how a formwork crew is built affects whether a design is built as drawn.
What WHS duties apply to formwork design?
WHS duties come in layers, and each carries different weight:
1. The WHS Act sets duties for businesses, designers and others, including the duty to consult, cooperate and coordinate.
2. The WHS Regulation adds specific obligations, such as the designer safety report. In NSW, the WHS Regulation 2025 replaced the 2017 Regulation the Code cites.
3. Codes of practice can be used by courts as evidence of what is reasonably practicable, but an equivalent or higher standard also complies.
4. AS 3610 is the technical standard the Code refers to.
5. Specifications and contracts can go further than the standard.
No certificate transfers a duty, and following a standard alone doesn’t satisfy every WHS obligation. Other states differ in detail.
What does the NSW Code of Practice say about formwork?
The Code of Practice: Formwork is approved under section 274 of the NSW WHS Act and commenced on 26 June 2020. On documentation, it says:
- Designs with unusual features creating construction hazards need a designer safety report, passed to the principal contractor.
- The principal contractor and formwork contractor should check the design complies with the AS 3610 series before work starts.
- Drawings should be certified by a competent person, such as a structural engineer.
- Installed formwork should be inspected and certified in writing before the pour, and alterations need the designer consulted and drawings updated.
A November 2024 SafeWork NSW safety alert reported more inadequate designs and certifications. It expects site-specific designs by a competent person with formwork experience and civil or structural engineering qualifications.
What documents make up a formwork design package?
A formwork design package is the coordinated set of drawings, calculations and information showing how formwork will be built, loaded, checked and removed. Contents vary, but an engineered NSW package commonly includes the documents below.

Figure 1. Typical components of a formwork design package. Exact contents depend on the project and applicable requirements.
What should formwork general arrangement drawings include?
The layout against the structural grid, set-out points, dimensions and levels, panel arrangements, component locations, sections, elevations and interfaces with the permanent structure. The Code also expects maximum deck point loads to be shown. Every sheet needs a revision and status.
What should formwork design calculations cover?
The design basis, loads and combinations through erection, pour and stripping, component capacities, stability, bearing, connections, and the standards and manufacturer data relied on. The Code asks designers to set vertical pour rates for walls and columns. Calculations must match the drawn arrangement. Formwork loads and failure modes are covered separately.
Tie and prop schedules
Component type, location, spacing, configuration, capacity limits, fixings and drawing references. A schedule that disagrees with the drawings is a defect in the package.
Formwork sequence drawings
The order of work, configuration at each stage, inspection points and programme links, with the assumptions for each stage. This is where sequencing form, reo and pour meets the design.
Backpropping design documentation
Where required, backpropping design is a separate deliverable, coordinated with the structural engineer because the Code says backpropping follows their design. For the terminology, see high strutting, propping and backpropping explained.
Notes, assumptions and certification
Standards and editions, finish class, materials, concrete information affecting pressure, load restrictions, stripping criteria and design limits, plus designer details, check records, certificates and manufacturer data. Undocumented assumptions are where teams talk past each other.
How do formwork drawings coordinate with structural drawings?
The structural engineer designs the completed structure, and the formwork designer designs the temporary works that build it. They meet at levels, set-downs, penetrations, embedded items, pour sequence and construction loads on floors below. A formwork package shouldn’t quietly change the permanent design. Discrepancies go to the responsible designer, which is why early drawing reviews matter and temporary works shape permanent outcomes.
Who signs off formwork design in Australia?
There is no single national rule. The answer comes from the state’s WHS framework, the specification, the contract and the complexity of the formwork. In NSW, guidance points to design by a competent person, drawings certified by a competent person such as a structural engineer, and installed formwork certified before the pour. SafeWork NSW adds that final certification should be no more than 48 hours before the pour and never forward-dated. For conventional slabs, the Code allows standard details or manufacturer publications to be referenced.
Keep four signatures distinct: the designer’s, the checker’s or independent verifier’s, the builder’s approval for use, and the certificate that the installed formwork matches the design. None replaces another, or correct installation.
How should a formwork design package be reviewed and issued?
A common sequence, adjusted to project and regulatory requirements:
1. Confirm scope, designer, standards and finish class.
2. Obtain current structural drawings and specifications.
3. Prepare drawings, calculations, schedules and sequence documents.
4. Coordinate interfaces with the structural engineer.
5. Check, then certify or approve where required.
6. Issue the correct revision to site and manage changes through the designer.
7. Verify the installed arrangement at each hold point.
Issued drawings aren’t approved drawings, and a reviewed design doesn’t guarantee the built work matches it.
What Future Form’s projects show about off-form work
Future Form’s projects include off-form structural elements and curved jumpform cores reaching 28 storeys at Smith St, Parramatta, and a curved off-form dome façade at Castle Residences in the Sydney CBD. These examples aren’t assigned an AS 3610 class here. That belongs to each project’s documentation.
One team from drawing to pour: formwork design with Future Form
Future Form holds formwork planning and engineering capability in-house, so the team engineering the formwork works with the team building it. That shortens the documentation chain. Our formwork engineering models pour sequences before construction, and we review structural drawings early to raise interface issues while they’re cheap to fix. It doesn’t replace independent checking or approvals where they’re required.
If you’re weighing Class 2 against Class 3, compare real surfaces from completed pours with the specification each was built to. Our formwork, jumpform, high strutting and concrete services run across NSW and the ACT under triple ISO-certified systems.
6 FAQ
1. What does AS 3610 cover?
AS 3610 covers formwork for concrete. AS 3610.1:2018 covers documentation and off-form surface finish, and AS 3610.2 (Int):2023 covers design, erection and removal.
2. What is the difference between AS 3610 and AS 3610.1?
AS 3610.1 is Part 1 of the series, dealing with documentation and surface finish. Design and construction sit mainly in AS 3610.2 (Int):2023.
3. How much does a Class 1 concrete finish cost?
There is no fixed price. Class 1 is the most demanding and usually most expensive class, but cost depends on form face, detailing, workmanship and inspection.
4. Who signs off formwork design in Australia?
It depends on the state, specification and contract. In NSW, a competent person, such as a structural engineer, typically certifies the drawings and the installed formwork.
5. What documents make up a formwork design package in NSW?
Typically general arrangement drawings, calculations, tie and prop schedules, sequence drawings, backpropping design where needed, design notes and certification records.
6. Does the structural engineer need to approve formwork drawings?
Not automatically. They should review interfaces with the permanent structure, such as backpropping and construction loads. Certification follows project requirements.
From specified finish to certified pour
Formwork design starts before the formwork does. Confirm which parts of AS 3610 and which project requirements apply, and settle the finish class early, because it shapes the form face, layout and cost. Name who prepares, checks, certifies and approves the design, and keep drawings, calculations, schedules and sequence documents aligned with the structural design. Treat WHS duties and certification as part of the programme, not paperwork at the end.
If you have an upcoming structure or need formwork design support, speak with a Future Form expert.
The formwork comes down after the pour. The documentation behind it is what keeps the concrete up.