High strutting is an engineered temporary support structure that carries formwork, fresh concrete and construction loads where the soffit sits well above the floor below, or where loads, spans or geometry rule out a standard prop layout. Frames or towers are braced and connected as one structure, and loads travel down into the slabs and structure beneath.
That last point is where the risk sits. This article defines the terms project teams mix up, then follows the load path through design, sequencing, scaffold interfaces and certification. It’s part of Future Form’s wider coverage of formwork in construction.
Key takeaways
- High strutting is a designed structure, needed where height, loads, spans or geometry go beyond conventional propping. It isn’t just longer props.
- The six terms do different jobs. Falsework is the whole temporary support. High strutting, shoring and propping provide it. Backpropping and reshoring manage load through slabs already cast.
- Loads don’t stop at the base plate. They travel into immature slabs and lower levels, and each one must be checked at every stage.
- Backpropping and reshoring follow the design, with sequences documented and changed only through the engineer.
- Stability governs tall arrangements. Bracing, connections and bearing matter as much as component capacity, and scaffold interfaces must be designed in.
- Future Form designs and supplies high-strutting and scaffold systems, with engineering and certification included.
When does a project need high strutting?
A project needs high strutting when support height, construction loads, span or geometry exceed what a standard prop layout can safely carry. There’s no universal height threshold. It depends on the structure, the system and the construction methodology. Common triggers:
- Deep basements: tall floor-to-floor heights, staged excavation and tight access, with supports bearing on recently poured slabs or prepared ground.
- Transfer structures: deep, heavy slabs and beams whose construction loads are significant and whose support layouts must work around existing columns and walls.
- High floor-to-floor heights: lobbies and podiums where overall stability, bracing and connections govern the design.
- Atria and open spaces: voids that limit support locations, lengthen spans and force scaffold and supports into the same space.
- Long-span soffits: wide soffits where support spacing, head arrangements and the slab below need close coordination with the formwork.
High strutting, shoring, falsework, propping, backpropping and reshoring: what is the difference?
These terms get used loosely on site, but each describes a different design function. Project documents should define how they’re used.
High strutting
High strutting is falsework that supports formwork or construction loads over significant height or in demanding configurations. Frames, props, bracing and connections act as one engineered structure, so it’s assessed as a complete arrangement, including the structure below.
Shoring
Shoring is temporary support that holds up or stabilises a structure, or part of one, during construction, alteration or repair. It’s a broad term that can also mean excavation support or propping an existing building, so check what a document intends.
Falsework
Falsework is the temporary structure that supports permanent works until they can support themselves. The NSW Code of Practice: Formwork says it includes foundations, footings and all structural members supporting the permanent elements, including back props, props and shoring. Safe Work Australia’s guide to falsework covers it in more detail.
Propping
Propping is the use of temporary vertical supports, usually adjustable props, to carry loads during construction. One prop’s rated capacity doesn’t establish the capacity of the system, which also depends on extension, bracing, bearing and layout.
Backpropping
Backpropping is the installation of temporary supports under slabs that are already poured, so loads from the work above are shared across several levels. The NSW Code says it should be installed to the structural engineer’s design. It’s a load-sharing system, not props left behind.
Reshoring
Reshoring replaces original supports with new ones after formwork is stripped, in a planned sequence. ACI 347.2R-17 describes reshores as installed snug, without initially carrying load. Reshoring changes the supports under a stripped slab. Backpropping supports the lower slabs carrying load from above. Some contractors use the words interchangeably, so drawings should state which is meant.
Table 1. The six temporary support terms compared
| Term | What it means | Primary purpose | Typical context | Place in the wider arrangement |
| High strutting | Engineered falsework at height or in demanding geometry | Carry formwork and pour loads safely | Basements, transfer levels, atria, long spans | A complete structure within the falsework |
| Shoring | Temporary support or stabilisation | Hold up or stabilise a structure | Slabs, excavations, refurbishment | Broad term; meaning varies |
| Falsework | All temporary structure supporting the permanent works | Carry loads until self-supporting | All in situ concrete | The overall system |
| Propping | Temporary props carrying load | Vertical support | Conventional slabs and beams | Components in a designed layout |
| Backpropping | Supports under previously cast slabs | Share loads between levels | Multi-storey slab cycles | Extends the load path down |
| Reshoring | Reinstalled supports after stripping | Support a stripped slab | Early stripping, cycle reuse | A defined stage in the sequence |
Usage varies between contractors and jurisdictions.
What systems are used for high strutting?
A high strutting formwork system typically combines proprietary heavy-duty frames or modular support towers, high-load props, bracing, adjustable base and head jacks, and connectors such as U-heads. Some scaffold systems are also designed for load-bearing falsework. Capacities, configurations and limits differ between systems, and the manufacturer’s documentation sets them out.
The NSW Code expects proprietary components to be used to the manufacturer’s specifications and a competent person to assess any mixing of manufacturers. Hire documentation, such as Shore Hire’s Trishore operating instructions, stresses rated loads, bracing and correct installation. Choose for the structure, its access and the programme. The wider options are covered in types of formwork in construction.
How is a high-strutting system designed?
The design checks the complete arrangement: the supported formwork, the loads, the support system and the structure receiving them. It covers:
- Geometry, height, layout and spacing
- Load combinations at every stage, and vertical load transfer
- Horizontal stability, bracing, lateral restraint and connections
- Base bearing, head details, eccentricity and installation tolerances
- Erection, pour and removal sequences, access and inspection
- Manufacturer limits and the capacity of the supporting structure
A check of vertical prop capacity alone isn’t enough, because in tall arrangements stability usually governs. Pour loads and form pressures are a separate subject under structural safety in formwork, and documentation requirements sit under AS 3610 formwork design and documentation.
How do loads transfer through an immature concrete slab?
Loads pass from the base plates into the slab directly below, then through backprops to lower levels and on to columns, walls, footings or ground able to carry them. Every slab in that path has to be checked for its current stage.
A slab poured days earlier may not have the strength or stiffness the permanent design assumes. The Concrete Centre’s work on early age construction loading notes that construction loads can be among the most significant a multi-storey frame experiences. How load is shared depends on concrete strength development, stiffness, the number of supported levels and the pour sequence.

Figure 1. A conceptual backpropping and reshoring sequence. It’s illustrative only, not a construction design.
Days elapsed don’t prove readiness. Temperature, mix and curing all affect strength gain, and the permanent design doesn’t automatically cover temporary load cases. The NSW Code bases stripping authorisation on the design, verified concrete strength and time elapsed, confirmed in writing by a competent person.
Why is backpropping often overlooked?
Attention goes to the deck being poured, not the slabs underneath. Once the props above are certified, lower floors can look finished, yet they’re carrying load, and each new level adds more.
That’s why backpropping needs to be designed and documented with the structural engineer’s input. Drawings should show the levels and locations, design assumptions, slab strength information, construction stages, installation and removal sequence, restrictions, inspection requirements, and how changes are approved. Removing a “spare” prop without review can redirect the load path, which is how temporary works shape permanent structural outcomes.
How are reshoring sequences planned?
A reshoring sequence sets out when original supports come out, when reshores go in and when lower supports can be released. Each stage has its own design basis, tied to the pour programme and each slab’s strength development. It isn’t simply putting props back after stripping, and any change needs engineering approval first. Linking the form, reo and pour sequence to the temporary works design tells the crew, across one slab cycle, which supports stay and which can move.
How do scaffold and access systems interact with high strutting?
Scaffold and high strutting often share space but do different jobs. Safe Work Australia’s guide to scaffolds and scaffolding describes a scaffold as a temporary structure supporting access or working platforms. High strutting supports the permanent works. The NSW Code allows scaffolding equipment to be used as falsework, but only where the system and design provide for it. In NSW, erecting falsework that will support scaffold platforms with a fall risk over 4 m requires a scaffolding high risk work licence.
At the interface, identify whether each component provides access, support or both. Check how platforms, ties and loading bays affect stability and loads, keep clearance for installation and inspection, and coordinate both designs wherever they connect. Adding scaffold always changes the structure it’s attached to.
What engineering and certification are required?
High strutting usually needs project-specific engineering. The certification pathway depends on the design, the system, the project and the jurisdiction. Keep these roles separate:
1. Manufacturer documentation: component data and system limits
2. Project-specific design: calculations, general arrangement drawings, schedules and sequences
3. Design checking or independent review, where required
4. Engineering certification and approval under the project’s arrangements
5. Installation inspection and verification before loading
A SafeWork NSW safety alert expects site-specific designs by a competent person and certification of installed formwork before the pour. Manufacturer data doesn’t replace project design, and a certificate doesn’t replace competent installation. Duty-holder obligations are set out in formwork safety and structural compliance in Australia.
What can go wrong with tall support structures?
In tall supports, stability rather than strength often governs, so small details matter. A component failure, such as a damaged head jack, may stay local. A system failure happens when one deficiency redistributes load until the whole arrangement loses stability.
Table 2. Failure modes in tall support structures and practical controls
| Failure mode | Contributing condition | Practical control |
| Instability or buckling | Missing bracing, poor lateral restraint | Bracing installed as drawn and checked |
| Connection failure | Missing or incompatible components | One system, inspected against schedules |
| Base failure or settlement | Soft or uneven bearing, washout | Bearing assessed, sole plates as designed |
| Overloaded supporting slab | Immature concrete, too few backpropped levels | Stage checks with verified strength |
| Premature removal or alteration | Unreviewed changes to supports or sequence | Changes only through the designer |
None of these is inevitable. Each is controlled through design, installation and inspection.
How should high strutting be coordinated on site?
Design, supply, installation and inspection need to work from the same information. Responsibilities vary by contract, but a practical sequence is:
1. Confirm requirements, structural drawings and design scope.
2. Select a system and confirm its limits and availability.
3. Design the arrangement, including load paths, backpropping, reshoring and scaffold interfaces.
4. Issue drawings, review and approve, then install and inspect at each hold point.
5. Manage changes through the designer until release conditions are met.
Supervisors need current drawings on hand, which is part of how a formwork crew is built.
Who designs and supplies high-strutting scaffold systems in Sydney?
Future Form designs and supplies high-strutting and scaffold systems in Sydney, across NSW and the ACT. Its services include engineered strutting and scaffold systems alongside formwork, jumpform and concrete, with pour sequences modelled through in-house formwork engineering.
Its projects include Smith St, Parramatta, where the tower’s high-strutting soffit and columns added complexity alongside curved jumpform cores, and The Langston in Epping, where Future Form formed four basement levels, each with more than 5,000 m² of horizontal formwork.
From soffit to supporting slab: high strutting designed and supplied by Future Form
Future Form designs and supplies high-strutting and scaffold systems for deep basements, transfer structures and long-span soffits, with the engineering and certification included rather than referred out. One team engineers the arrangement, supplies the system and works with the installing crews, so load paths, backpropping, reshoring and scaffold interfaces are coordinated in one place. Scope follows each project’s requirements, and installation and inspection remain essential.
Planning a deep basement, transfer level or long-span soffit? Send your structural drawings, levels and programme so the right high-strutting and scaffold solution can be assessed. Talk to Future Form about your project.
6 FAQ
1. What is high strutting in construction?
High strutting is engineered falsework supporting formwork and construction loads over significant heights or in demanding configurations, designed as one braced structure down to the slab below.
2. What is the difference between propping and backpropping?
Propping supports the structure being built. Backpropping supports already-poured slabs below, so construction loads are shared across levels. Both follow the engineer’s design.
3. What is the difference between falsework and shoring?
Falsework is the whole temporary structure supporting permanent works until self-supporting. Shoring is a broader term for temporary support or stabilisation, and its meaning varies by context.
4. How do loads transfer through an immature concrete slab?
Loads pass into the slab below, then through backprops to lower levels and the supporting structure. Capacity depends on each slab’s strength at that stage, so the engineer checks every stage.
5. Can scaffold systems be used for high strutting?
Only where the system and design specifically provide for it. Access scaffold isn’t automatically suitable for supporting formwork, and shared arrangements need coordinated design.
6. Does high strutting require engineering certification?
It usually needs project-specific engineering, and certification depends on the project and jurisdiction. In NSW, installed formwork is expected to be certified before the pour.
Every load path ends somewhere: design high strutting from the ground up
High strutting works when it’s treated as a complete engineered structure, braced, connected and checked down to whatever finally carries the load. Concrete strength, backpropping and reshoring decide whether lower levels can take their share, and scaffold interfaces belong in the design from the start. Engineering, certification and correct installation all need to line up before the pour.
If you’re planning a deep basement, transfer structure or long-span soffit, discuss your high-strutting and scaffold requirements with Future Form.
Props come out once the slab can stand on its own. Until then, every pour above depends on the load path planned beneath it.